Today, in Mintia, the first ignition of gas turbine no. 1 from the new power plant took place. "Today, in Mintia, the first ignition of gas turbine no. 1 from the new power plant took place. This is an important technical milestone for one of the most significant energy investments in Romania in recent years. In June, when I was on site, the project was over 80% completed. Since then, work has progressed step by step: on June 15, the facilities through which the turbine connects to the grid were energized, and today the turbine operated for the first time on natural gas. Next comes the completion of tests, synchronization with the grid, and the first megawatts delivered to the National Energy System. The two gas turbines will have a combined capacity of approximately 1,100 MW," said Ilie Bolojan on Thursday evening in a Facebook post. #energie #centralaMintia #gaznatural (translated)